Brockham Water Main Replacement

SES Wateris currently making a major investment in Brockham to secure safe and reliable drinking water supplies for the village’s homes and businesses.

SES Water has stated that the current water main, which runs the length of Brockham Lane and Middle Street and dates back to the 1920s, has reached the end of their operational life.

The project involves laying approximately 1.2km of new main along Brockham Lane and Middle Street. It is a major project that will be completed in three phases: 

Phase 1, Junction Closure – A25 Junction to The Cedars
Monday 23rd September to mid November

Click here to download an update from Compass setting out changes to the 32 bus

Phase 2, Temporary Traffic Signals – Cedars to River Mole Bridge
Mid-November to January 2020

Phase 3, Road Closure – River Mole Bridge to Wheelers Lane
January 2020 to July 2020.

To learn more from SES Water click here.
To monitor updates relating to road closures and diversion routes click here.

September 20, 2019